Infrared Patching

TRADITIONAL PATCHING

step1
Step 1:

Area to be repaired.

step2
Step 2:

Infrared heating unit is lowered to within 6" of the pavement.

step3
Step 3:

Having heated the area to be repaired, the softened asphalt is raked and cleared of impurities.

step4
Step 4:

New asphalt is stored at 300° and added to the repair area.

step5
Step 5:

New and original asphalt is blended and raked level.

step6
Step 6:

The edges are first rolled to bond the new asphalt with the original asphalt. The entire area is then compacted with a vibratory roller.

step7
Step 7:

The repair becomes a seamless part of the original asphalt.
Patch is completed in approximately 15 minutes.