Area is staked, topsoil is removed and the site is excavated to a depth of 8". Existing pavement that will be butted up to is snaplined and sawcut.
A 6" compacted base of high grade road material is built 3" at a time. This is continually watered and rolled to ensure maximum compaction, eliminating the need to delay paving while the base settles.
The base material is graded with a final watering and rolling. It is checked continuously for water flow to eliminate the possibility of puddles. It is now exactly the same as the final paved job, except it is 4" wider and 2" lower.
Hot mix asphalt (290°) is loaded into the paver machine. Crew members constantly monitor and adjust the depth and check the grade as the paver evenly lays the asphalt.
Maximum compaction is achieved by immediately rolling the hot asphalt with a vibrating steel wheel roller. The edges are trimmed using string lines and the area is cleaned up. After slight cooling the job rolled again. This "cold rolling" removes any creases or lines leaving a smooth finished asphalt pavement.
The finished job is barricaded off and allowed to cool completely.